11-29-2023 11:07 PM

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-29-2023 11:57 PM
Hi @naresh g ,
Can you please add what is expected & some explanation to the expected numbers.
This understanding will allow to suggest.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-30-2023 12:51 AM
Hours part wrongly showing in month of May remaining months 160 hours showing but in month of May showing 1096 hours showing
Could you please help on this issue
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-30-2023 12:54 AM
Hi namita,
Regarding resource report month of May it showing 1096 hours but remaining month it showing 160 hours
That is the iam facing issue could you please help on this

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-30-2023 05:50 AM
Hi @naresh g ,
I am expecting that you can access the instance as pps_admin.
Typically this kind of issue happens when the resource aggregates gets corrupted due to some reason.
With the limited information in hand, I would suggest you to check if below steps resolve the issue:
1. Login as pps_admin
2. From left navigation panel select, Resources -> Resource Diagnostics
3. Select the different options present on the UI and click on 'Run Diagnostics'
4. If there are any issues, system will list them and from there it will be easy to understand the root cause and take the corrective action.
Let me know if the above suggestion works for you.