Showing active and future work in SPW
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hello,
Hoping someone else has a good way to solve for this. When planning through SPW how do you see in an initiative with active projects rolling up to programs, stand alone projects rolling up to initiatives, and demands rolling up to an initiative in one view?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago
@RandiW1611 You cannot view items in an hierarchy if they are all not aligining to the lens entities as per your lens.
In your example, you cannot have some projects tied to program and some tied to initiatives and view them both on a single view.
However, you can have two different lenses to reflect that structure and view them in two different portfolio plans.
I recommend creating a dummy program or a miscellaneous program so that all the projects and demands follow same hierarchy structure.