We are working on Creating a Project in SPM and what we see is we have created an 

> Agile Phase and linked with Story 1, Story 2, Story 3

> Story 1 is tagged with Sprint 3 (Start date Jan 01 2025 - End date Jan 16 2025)

    Story 2 is tagged with Sprint 4 (Start date Jan 20 2025 - End date Jan 31 2025)

    Story 3 is Tagged with Sprint 9 (Start date March 03 2025 - End Data March 14 2025)

 

Now when we check the Gantt Chart the Agile phase is not getting the roll up happening and showing the progress.

 

Question is : should agile phase have stories with sequential sprint planning  ?

 