Start and End date validation issue when creating a resource assignment from Project Workspace

art_jones
Kilo Sage

When creating a resource assignment from a task in project workspace:

  • select the WBS item (a task)
  • click the Add Resource button
  • a blank resource assignment row appears with start and end date pre-filled (based on the task)
  • enter group and role
  • workspace generates date validation error (see below)
  • the only way to get around the error is to set the start date a day after the tasks start date, and the end date a day after the task's end date. I assume this is b/c the task dates are date/time and the resource assignment's dates are date.
  • Am I missing some setup, or is this expected?
  • Is there any way to have the defaults set to a date that works?

art_jones_0-1714583785044.png

art_jones_1-1714583814594.png

 

Thanks!

1 REPLY 1

Christine B
Tera Contributor

Does anyone have a solution for this please?