Sub Project Cost Rollup To Parent Project
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-15-2017 03:42 PM
Hello,
I'm struggling to be able to rollup my sub project costs to the parent project. OOB this doesn't seem to happen both on Helsinki or Istanbul.
If we look at the OOB field "Actual Cost" I can roll this up from Project Task to Sub Project however I then want to be able to rollup all my Sub Projects to the Parent Project, at the moment "Actual Cost" on the parent displays as $0 even though there's a total in the Sub Project.
Has anyone delt with this before? It's seems like it should work OOB after enabling it under the Project > Setting > Preferences. Or at least there might be a simple business rule i could implement?
Thanks for any help anyone can offer.
Chris

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-15-2017 05:04 PM
Under Projects > Settings > Preferences - there is a setting:
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-15-2017 05:12 PM
Hi Michael,
Thanks for the response. I have this option already checked and it works when rolling up from Project Task to Sub Project however this doesn't seem to work if I want to continue the rollup from Sub Project to the Parent Project.
Do you know how you might rollup a field such as Actual Cost from Sub Projects to the Parent Project?
Thanks
Chris

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-15-2017 05:32 PM
Hmmm, I thought it rolled them all to Parent. Might need kellykaufmann or ITSMgal to help.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-15-2017 05:39 PM
Yeah I thought the same thing. I'm just trying it on OOB fields at the moment. In my dev instance with PPS with Financials activated and that option in the Project > Settings > Preferences checked it only does rollup from Project Task to Sub Project.
I've just been trying this for "Actual Cost" field as this is OOB to keep it simple.
Thanks
Chris