Hi All,
In resource management, we have BAU and Project allocation which has different resource plans. Is it possible to add a validation that will set the hours daily to a maximum of 8 hours per day?
In my screenshot, the allocation is for 2019-03-01 and that includes BAU and PROJECT. However if we total the hours for that one day [2019-03-01] it exceeded the 8 hours (the total hours of work per day)? Has anyone done any validation that will either restrict to allocate more hours if it reached 8 hours already?
Thanks in advance.
Ramel
- Labels:
-
Resource Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-12-2019 02:57 AM
Navigate to Resource > users
and fill in Average Daily FTE Hours/Hours Per Person Day field
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-25-2019 06:13 PM
Thanks for the response dvp. I have tried putting 8 hours on Average Daily FTE Hours/Hours Per Person Day but when I tried creating a resource plan it still is allocating more than 8 hours for 1 day.
That is a combination of BAU and PRJ which should only be maximum total of 8 hours.
Thanks,
Ramel

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-25-2019 06:30 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-25-2019 06:42 PM
Yes dvp, I clicked on Update Resource Capacity and also tried to Update Resource Aggregates but it still allows to allocate when I create a new resource plan and still makes it more than 8 hours daily. It seems like it is not considering that 8 hours set on the daily/fte hours.