Total the hours for the resource allocation daily to a maximum of 8 hours per day
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-12-2019 12:32 AM
Hi All,
In resource management, we have BAU and Project allocation which has different resource plans. Is it possible to add a validation that will set the hours daily to a maximum of 8 hours per day?
In my screenshot, the allocation is for 2019-03-01 and that includes BAU and PROJECT. However if we total the hours for that one day [2019-03-01] it exceeded the 8 hours (the total hours of work per day)? Has anyone done any validation that will either restrict to allocate more hours if it reached 8 hours already?
Thanks in advance.
Ramel
- Labels:
-
Resource Management
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-11-2020 11:26 AM
What is the schedule that is applied to the user?