Unable to block workdays on a project

Faris  Kindilch
Tera Contributor

I have been trying to add the US Holidays to the Project Management schedule (which is 8 - 5 workdays) to make sure that all of our project timelines and calculations are correct. I have tried pretty much everything that I have read about schedules which includes: 

- Adding an already existing US Holidays child calendar to the Project Management calendar (with both include and exclude options)

- Adding these holidays directly into the Project Management calendar as 'Time Off' days

- I removed and rebuilt the project plan after creating/updating each calendar

 

what am I missing? 

 

Thank you, 

Faris  

 

0 REPLIES 0