Unable to create milestone for Project records

sieusaopolo15
Giga Sage

When I was browsing to explore functions in SPW I found that I can not create milestones for Projects only for Demands. Every project I opened have this specific warning info. How can I create milestone for projects ? Am I missing something in PPM side ?

sieusaopolo15_1-1759756003134.png

 

 

5 REPLIES 5

M Iftikhar
Tera Sage

Hi @sieusaopolo15,

 

To create a milestone in a project, add a new project task and set its duration to 0. This makes it a milestone. You can then link it with dependencies like any other task.

 

For detailed instructions, refer to the official documentation: 

Create a milestone

Additional helpful resource:

Customizing milestones display on roadmap in Strategic Planning Workspace

 

Thanks & Regards,
Muhammad Iftikhar
If my response helped, please mark it as the accepted solution so others can benefit as well.

Thanks & Regards,
Muhammad Iftikhar

If my response helped, please mark it as the accepted solution so others can benefit as well.

Hi @M Iftikhar , the links you provided is in Planning Console but in my case it is Strategic Planning Workspace

Anand2799
Tera Guru

Hi @sieusaopolo15 ,

 

You are trying to create milestone on planning items.

Did you set up integration b/w project planning item and projects?

 

To resolve the issue, follow these steps:

  1. Navigate to Portfolio Planning > Integration.
  2. Open the active integration record.
  3. In the Table Map related list, open the entry for pm_project.
  4. Confirm that the Milestone table map field is populated (not empty).

Anand2799_0-1759759909936.png

 

 

Thanks

Anand

Hi @ Anand2799 , I did the mapping but it's still doesn't work