When I was browsing to explore functions in SPW I found that I can not create milestones for Projects only for Demands. Every project I opened have this specific warning info. How can I create milestone for projects ? Am I missing something in PPM side ?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 hours ago - last edited 3 hours ago
Hi @sieusaopolo15,
To create a milestone in a project, add a new project task and set its duration to 0. This makes it a milestone. You can then link it with dependencies like any other task.
For detailed instructions, refer to the official documentation:
Additional helpful resource:
Customizing milestones display on roadmap in Strategic Planning Workspace
Thanks & Regards,
Muhammad Iftikhar
If my response helped, please mark it as the accepted solution so others can benefit as well.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 hours ago
Hi @M Iftikhar , the links you provided is in Planning Console but in my case it is Strategic Planning Workspace
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 hours ago
Hi @sieusaopolo15 ,
You are trying to create milestone on planning items.
Did you set up integration b/w project planning item and projects?
To resolve the issue, follow these steps:
- Navigate to Portfolio Planning > Integration.
- Open the active integration record.
- In the Table Map related list, open the entry for pm_project.
- Confirm that the Milestone table map field is populated (not empty).
Thanks
Anand
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 hours ago
Hi @ Anand2799 , I did the mapping but it's still doesn't work