This is a brand new project record created from a Demand
Planned End Date cannot be altered, when I hover over I see Record has children so this field is calculated from child values
Planned duration also cannot be altered with the same message as above
Project Status is Pending
Project Tasks are empty
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎11-06-2018 10:26 AM
Found the script. Its here:
/nav_to.do?uri=%2Fsys_ui_macro.do%3Fsys_id%3D5046d5cac0a80a6915830b45b9619223%26sysparm_record_target%3Dsys_ui_macro%26sysparm_record_row%3D1%26sysparm_record_rows%3D1%26sysparm_record_list%3Dsys_id%253D5046d5cac0a80a6915830b45b9619223%255EORDERBYDESCsys_updated_on
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-18-2019 03:18 PM
Same issue, can someone please help?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-19-2019 03:23 AM
If a Project has any Project Task or Sub Project, then Planned Start/End date filed is non-editable.
The Planned Start/End date field of project is set based on it's Project Task/Sub Project's Planned start/end date. It aggregates from all of its dependent and set the min planned start date and max planned end date to the Top Task/Project.