When we have multiple Resource Management Schedules how to set default value for Resource Properties
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-06-2022 09:13 PM - edited 12-06-2022 10:01 PM
Hi All,
Following is the setup that am planning for my requirement. Please suggest me if this is correct or I can do it in any better way.
I need to set up Resource schedule for Resources where we have 4 different regions involved.
Let’s say Region A, Region B, Region C and Region D.
For Region A and Region B daily working hours : 8
For Region C daily working hours : 7.6 (7 hours 36 minutes)
For Region D daily working hours : 9.6 (9 hours 36 minutes)
List of Holidays for all 4 regions are different.
Since out of the box Resource Management Schedule is 8 hours per day , I need to create additional resource schedules.
In this scenario, since list of holidays are different for each region, I should create 4 holiday schedules to add as child schedule for resource schedule.
So I will create 4 holiday schedules:
RegionA_holiday schedule
RegionB_holiday schedule
RegionC_holiday schedule
RegionD_holiday schedule
I will create 4 Resource schedules – 1 Resource schedule per region
RegionA_Resource schedule and add RegionA_holiday schedule as child to include
RegionB_Resource schedule and add RegionB_holiday schedule as child to include
RegionC_Resource schedule and add RegionC_holiday schedule as child to include
RegionD_Resource schedule and RegionD_holiday schedule as child to include
Questions:
- What value should I set up for the property Default Schedule Name ?
- How to associate the regional schedules to resources so the capacity calculation is as per regional schedule? Should I associate the RegionA schedule to all the users of RegionA on User record? Since we have thousands of users , is there any easy way to associate Schedule to those users?
- What value should I set up for the property Average Daily FTE Hours/Hours Per Person Day ?
- Default Project Management Schedule is 8 hours. Should I create multiple Project schedules per region as per their daily working hours or keeping one Project Schedule is fine?
- While creating a Schedule entry if I leave the field Repeat until as blank then till when the schedule entry will be valid?
- Schedules creation is considered as data and can't be moved via update sets? We need to create these data in Production or can we do export/import from test to prod? What is the best practice ?
I am new to ServiceNow, any help is much appreciated.
Thank you,
Anusha
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-06-2022 09:21 PM - edited 12-06-2022 09:29 PM
Hi,
@Namita Mishra @abhinaykumar @Rajesh_Singh ,
I am tagging you to this post for better reach, as I have seen you answering queries related to this topic. Please help

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-11-2022 02:47 AM
Dear Anusha,
Sorry for late response, i was on leave for mount everest trek. just back yesterday.....here are responses
- What value should I set up for the property Default Schedule Name ? - Leave it empty, since you have different scheduled for each users
- How to associate the regional schedules to resources so the capacity calculation is as per regional schedule? - Should I associate the RegionA schedule to all the users of RegionA on User record? Since we have thousands of users , is there any easy way to associate Schedule to those users? - Under Resources > Users (once you opne any user record you can see "Schedule" field on the user record, you can update there
- What value should I set up for the property Average Daily FTE Hours/Hours Per Person Day ? Since you had already updated average hours in given particular user record - here you can Leave it empty or put 8 hours, property value will override with the hours you had updated in given user record
- Default Project Management Schedule is 8 hours. Should I create multiple Project schedules per region as per their daily working hours or keeping one Project Schedule is fine? just one project schedule is fine
- While creating a Schedule entry if I leave the field Repeat until as blank then till when the schedule entry will be valid? Didn't get your question what do you mean here?
- Schedules creation is considered as data and can't be moved via update sets? We need to create these data in Production or can we do export/import from test to prod? What is the best practice ? Use XML export or you can also add this to update sets
---------------
Regards,
Rajesh Singh

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-11-2022 04:21 AM

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-20-2022 08:09 PM
Thank you Namita, it was top most item of my bucket list!
---------------
Regards,
Rajesh Singh