why Actual Cost and Actual hours are not calculating from Time card in ResourcePlan

chanikya
Kilo Sage

Actual Cost and Actual hours are not calculating from Time card   in Resource Plan.

2.png

1 ACCEPTED SOLUTION

This business rule - Accumulate Hours/Cost to Resource Plan - is inactive. Is there a reason for that?


View solution in original post

9 REPLIES 9

I can't tell from your screen shot if the Time Card contains the Resource Plan.


Hi,



if you are intreated please look into this



Dev 19708


User id:   John.adams


Pawd: 1234


This business rule - Accumulate Hours/Cost to Resource Plan - is inactive. Is there a reason for that?


Hi Michael



You are really amazing


Thanks   for your help.


it is working now..!


You know what's funny?  I'm having the same problem on a basically fresh instance.
Why would htat business rule be Inactive if its critical to rolling up Time Card actuals?