Join the #BuildWithBuildAgent Challenge! Get recognized, earn exclusive swag, and inspire the ServiceNow Community with what you can build using Build Agent.  Join the Challenge.

Why cant the planned end date be changed for my project?

craigzeleznick
Kilo Contributor

I am trying to change a few planned end dates for different projects but the system is not allowing me. I thought it may be related to 1 project but it is the same for all projects.

I can go in and change the planned end date but once i refresh the screen or click the green check mark, it reverts to the original planned end date.

Why is this like this and how can this be fixed?

find_real_file.png

1 ACCEPTED SOLUTION

Craig,



The screen I shared is the creation of a project.



For the problem with weekend days it's the normal behaviour of PPM.


You have a default schedule on the "dates" tab wich determines on which days you can work :


find_real_file.png


Best regards,


Jorge De Araujo


View solution in original post

7 REPLIES 7

I just did some more testing and i was able to change the dates but it seems you can only change the dates to business work days(monday-friday)



Is this how it should work?



The original project end dates were 12-29-17 which was a friday and i was trying to change it to 12-31-17 which is a sunday and it wouldnt allow me to do that but if i changed it to that monday or the previous thursday it works fine.


Craig,



The screen I shared is the creation of a project.



For the problem with weekend days it's the normal behaviour of PPM.


You have a default schedule on the "dates" tab wich determines on which days you can work :


find_real_file.png


Best regards,


Jorge De Araujo


sameeralikhan
ServiceNow Employee
ServiceNow Employee

@Jorge de Araujo  The answer was helpful 🙂