change the status from work in progress to pending

Aurelijus Raudo
Kilo Contributor

hi,

need help on building the condition on sc_request table.

when request state changed to Work in progress, after 10 days change status to Pending.

 

Thank's

Aurelijus

 

1 REPLY 1

Muhammad Hamza
Kilo Sage

Hey Aurelijus Raudo ,

  • We need time when the request state changed to Work In Progress. For this, you can create a read-only date field.
  • Then, create a Business rule so whenever the state is changed to Work in progress. Populate the date field with the current date.
  • Create a Scheduled job (daily), which queries the sc_request records which are in Work in progress state, and then for each record, get the value of the date field and compare it with the current date.
  • You can use gs.datediff() to get the duration between dates.
  • Then, if the duration is more than 10 days update the record.

If this answers your question, kindly mark this as a Solution.

 