This article is for questions and answers for LAB2968 - Manage strategies to drive outcomes that create value with IT Business Management. This lab is being presented multiple times throughout the live K20 event May 5 - 7, 2020. During the live event, post your questions in the comments of this article, and one of our lab gurus will be happy to answer it.
- 9,149 Views
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Welcome, Mat! I am a big Chili Peppers fan too! Glad to have you in the session today!
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Welcome Nithin! We are excited to have you in the session!
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Great song choice, Howard! Welcome to lab session 2968!
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Text label is chopped off"...…" can you show entire labels on the bubble chart?
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Text label is chopped off"...…" can you show entire labels on the bubble chart?
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
You can hover over the bubbles and it will display the full name of either project/demands
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
I would prefer to have all of them display, so I'm not hovering over dozen+ bubbles...is it possible?
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
You can hover over the bubbles and it will display the full name of either project/demands
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Hello. I'm located in San Diego. I'm a technical consultant as gNIS, a ServiceNow partner that specializes in IT Business Management.
My karaoke song would be More Than Thankful by Brian Culbertson.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
How to assign multiple project managers for a single project. It is highly possible to have more than one project managers assigned. How to handle? We have only one project manager field in project form
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Nice song selection! We hope you enjoy the session!
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
You can add an additional PM field to your implementation, but the ServiceNow philosophy is to have one person ultimately responsible/assigned to every type of task.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
It is a good question. There is capability to customize the chart size including width and height of the chart in pixels. I believe the default is 600 and 450, respectively. Changing the chart size may provide additional text to display; however this will also depend on the number of characters used in the project/demand name.
Bear in mind, if you do have a dozen+bubbles, displaying the full text name of each project/demand will be very hard to read especially if they overlap.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
How would you manage BAU type changes where you have various defects/incidents and enhancements that are bundled together in a release? Items are not associated to any projects but are maintenance type changes. Would you treat all of the changes as a maintenance project with multiple deployments throughout the fiscal year?
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Hi Diana,
In my opinion, these are mostly BAU type changes and mostly don;t need a project to be stood up. You can block certain time of your resources to work on operational tasks so that it reflects proper resource capacity.
These smaller pieces of work can be managed within the ITIL process of change management.
I hope this makes sense.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
To piggyback off of what Steve said, you can add an additional PM field on the form. I have seen, especially in non-technical industries, whereby the need to show multiple project managers, for example, between a business project manager and a technical project manager.
Keep in mind, there is also a "Watch List"; if you need to further align additional individuals to the project for visibility.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
We have a release management feature that allows you to do that type of thing. https://docs.servicenow.com/search?q=Release+Management. If these are being worked on via a set of agile stories and sprints, you could use our Agile Management features to manage and track these and then use release management to move them into production.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
I’m in the Prioritize on Objective section of the Lab. When I impersonate Megan I only see the Upgrade Database demand not the Customer Mobile Application demand. Did I do something wrong?
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Did you remember to move it through to screening too?
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
thank you both
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Step 6 - it's easy to miss!
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
I must have missed that step
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
You can pop back in and quickly move it ahead 🙂
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Thank you I went back to the Customer Mobile Application demand to submit it and moved it to screening.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
If you hover over the bubbles you would see pertinent info which includes Risk, Value and Size. Right click on the Demand bubble and you could create a project out of it or access a link into the Demand.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
OOTB it is a PM assigned to a Project. However, within a Project Record you could have Sub Projects associated where different PMs can be assigned.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Quick question - can you please provide which 'related list' to add to the project record to show all change requests created for the project, as a whole (ie aggregation of all change requests created from tasks within the project)? TY!
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Check that you clicked on Screen for the Upgrade Database demand (Step 5 in the Prioritize on Objectives section).
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
In order to see the aggregate of all change requests from tasks within the project, you would need to configure the "Project Task Link -> Top Project" related list.
- Mark as Read
- Mark as New
- Bookmark
- Permalink
- Report Inappropriate Content
Thanks, Amel - I will try this out in my Sandbox!! Much appreciated 🙂