Process a change request
You can approve, implement, review, and close a change request.
Before you begin
Role required: itil, admin, sn_change_write, or change_manager
As part of processing a change request, ensure that you have detected any change conflicts and performed risk assessment
Procedure
- Navigate to All > Change > Open.
- Select a change request you like to work on.
-
You can perform the following actions on a change request based on your
role.
Option Description Approve or reject a change request Implement a change request Review a change request Select Review after reviewing the details on the change request. The change request is moved to the Review state. All open change tasks are set to Canceled.
Close a change request Select Close after entering the Close code and Close notes in the Closure Information section. The change request is closed.
Cancel a change request From the context menu, Select Cancel Change. Provide a reason for canceling the change and select Save. The change request is canceled and the reason for canceling the change is added to the Work Notes field.
Note:Users with approval_user role, who approve change requests, do not have access to the change request itself. The following information are made available within the approval record to help these users make the right approval decision:Manually created change tasks are not automatically closed or cancelled when state is changed from Implement to Review. You must first close the change tasks and to close the change request.- Number
- Requested by
- Configuration Item
- Type
- Planned Start Date
- Risk
- Planned End Date
- Impact
- Short Description
- Description
- Justification
- Implementation plan
- Risk and impact analysis
- Backout plan
You can also add approval history to the change request activity log. Click the activity filter icon and select Approval history from the list. When there is a change in the approval process, such as an approval, rejection, or comments, the activity log is updated.