Complete a resource plan
After all associated tasks and projects are complete or canceled, a resource manager can move the resource plan to the Complete state, which closes it.
시작하기 전에
The resource plan to be completed must be in the Allocated state.
Role required: resource_manager
이 태스크 정보
프로시저
결과
- The resource plan moves to the Completed state.
- If the completion date is earlier than the resource plan end date, the end date of the resource plan is updated with the completion date. If the completion date was entered later than the resource plan end date, the resource plan end date is retained.
- All the requested and resource allocations for the resource plan post the completion date are deleted. If there are any actual hours logged against an allocation, that allocation record isn’t deleted. But the allocated hours become zero and the actual hours are retained. The available and allocated hours for the resources are also updated in the aggregate tables.
예
- the resource allocation entry for January is deleted from the [Resource_Allocation] table.
- the resource allocation end date for December is updated to the completion date of the resource plan.
- the entries in the [Resource_Allocation_Daily] table for the December month post the completion date are deleted.
Example 2: If the same resource plan has Allocation type as Planned Duration, no allocations are deleted, and the end date of the allocation is updated to the completion date.