Reduce the duration of a resource plan
Reduce the duration of an allocated or confirmed resource plan and deallocate resources in one action without having to do it individually for each resource.
시작하기 전에
중요사항:
Role required: resource_managerResource plans in Resource Management will no longer be available for new customers from future releases.
You're encouraged migrate your existing resource plans to work on resource assignments which offers more flexibility and start using Resource Management Workspace.
Resource requester can move an assigned or unassigned resource assignment using Resource Management Workspace.
이 태스크 정보
You can reduce an allocated or confirmed resource plan only if the resource plan's end date is later than the current date.
You can reduce the duration of an operational resource plan only if its state is allocated.
프로시저
결과
- The end date of the resource plan is updated to the new reduced end date.
- The state of the resource plan remains the same.
- If no actuals are posted for the future in the resource plan, all allocated or confirmed hours of the resources are released.
- If actuals are posted for the future, then the resource plan end date is updated to the future date on which actuals are present, and all the allocated or confirmed hours of all the resources from the date on which actuals are present to the original end date are released.