Confirm a resource plan

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • As a resource manager, you can confirm or block the resources after a resource plan is requested. The resource plan must be in the Requested state to be confirmed.

    시작하기 전에

    중요사항:
    Resource plans in Resource Management will no longer be available for new customers from future releases.

    You're encouraged migrate your existing resource plans to work on resource assignments which offers more flexibility and Create resource assignments and operation resource assignments in Resource Management Workspace using Resource Management Workspace or Project Workspace.

    Resource managers can view and assign the unassigned resource assignments using Resource Management Workspace.

    Role required: resource_manager

    이 태스크 정보

    You can modify or cancel a resource plan that is in the Confirmed state.

    For a resource plan with the resource type as group, you can confirm resources only if the specified group has active members.

    프로시저

    1. Navigate to All > Resource > Resource Plans > Requested.
    2. Open the resource plan that you want to confirm and select Confirm.

    결과

    The resource plan moves to the Confirmed state and soft allocations are created.