Create a project task from a project

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 2분
  • Create tasks from the project form to break down project objectives into manageable units of work.

    시작하기 전에

    Role required: it_project_manager

    프로시저

    1. Navigate to All > Project > Projects > All.
    2. Select the project from the list.
    3. In the Project Tasks related list, select New.
    4. On the form, fill in the fields.
      For more information on project task form, see Project task form.
    5. Select Submit.

    결과

    The new task appears in the Project Task related list on the Project form. If time cards are in use, the application creates a time card for the resource.

    다음에 수행할 작업

    The value in the Percent complete field is related to the State field in the v3 application. If you change the percentage complete from 0 to any other value, the state of the task changes to Work in progress when you save or update the record. Likewise, if you change the state of the task to Closed complete, the Percent complete field is set to 100 and becomes read-only.

    If you change the state of a project task from Work in progress to Closed Skipped or Closed Incomplete, the Percent complete field retains the current value and becomes read-only.

    The Percent complete field appears in the Gantt chart for parent tasks as a light-colored bar (the part of the task that is complete). The bar overlaps the darker, underlying bar (the full task). For example, a Demo project is 5.41% complete as shown in a pop-up window. The Phase 1 task is about 50% complete (not shown in the pop-up window).

    The Project Tasks list and the Project Tasks related list on the Project form include a Dependency field. Any dependencies for a task, such as a parent task, are displayed in this field. Click a dependency record. See Predecessor dependencies in the planning console for a description of what you see in this column.