Change management Planned outage start date and Planned outage end date

lokeshd
Kilo Contributor

 When we are setting Planned outage start date and Planned outage end date, the tool is accepting Planned outage end date which is older than Planned outage start date. I mean planned outage end date is accepting the day before Planned outage start day. Is this an issue with all or the process varies from project to project? If all can i have a code update in Planned outage start date and Planned outage end date in #changemanagement  to reduce human error.

In the attached image u can see Planned outage end date has accepted time older to the Planned outage start date.

1 REPLY 1

Dr Atul G- LNG
Tera Patron
Tera Patron

Hi @lokeshd 

 

Simply, you can add the UI policy on the end date and it will be good to go.

 

UI Policy

End date is greater than start date

 

add in script

error message.

*************************************************************************************************************
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.

Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]

****************************************************************************************************************