Some stories will be part of more than 1 sprint.

Example: STRY123 was developed in Sprint 1, but validated and deployed in Sprint 2.

 

I would like to track how many sprints a story is part of.

I would like to track how many stories get added to a sprint after the sprint has started.

 

Currently, I am exporting the story list at the start of the sprint and at the end of the sprint.

 

Is there a better way to track this information?

2 REPLIES 2

AshishKM
Kilo Patron

Hi @KarrieDash ,

Did you try to create metric on story & sprint tables, later you can create report from metric table.

 

Thanks,

AshishKM


Please mark this response as correct and helpful if it helps you can mark more that one reply as accepted solution

Is there a way to configure the Metric Definition to only create Metrics for stories with a specific Project Name?