Can we create subtask for SCtask in flow designer??

soumya17
Tera Contributor

Hello,

 

Can we create subtask for SCtask in flow designer??

I have total 5 tasks actually. i want last 3 tasks should be the subtask of task2

i.e when task 2 is completed , there only remaining 3tasks should attach but not in RITM...

Can we achieve this with flow designer??

 

soumya17_0-1672312170803.png

 

Thanks

 

 

1 ACCEPTED SOLUTION

Create task record not catalog task


Thanks and Regards,

Saurabh Gupta

View solution in original post

6 REPLIES 6

Saurabh Gupta
Kilo Patron
Kilo Patron

Hi,
Technically this is posible.

 

You can create the record of task table and set parent field as the reference of sc_task.

 

 


Thanks and Regards,

Saurabh Gupta

Hi @Saurabh Gupta  

i tried the same..but it didnt work

 

soumya17_0-1672314481108.png

 

parent of the task3 i mapped to task2

 

Create task record not catalog task


Thanks and Regards,

Saurabh Gupta

create task also same scenario.