Error msg pop up when I update a project task record.

Yamja
Tera Guru

Hi,

I have a parent project task and child project task records. When I am trying to update planned end date of child project task,I am getting a pop up msg "Name field can not be empty". I tried looking at client scripts and business rules nothing has found. Please can anyone let me know the root cause. It is only happening when I update the planned end date, it still allowing me to update but getting a pop up msg.

 

Yamja_0-1678834400386.png

 

1 ACCEPTED SOLUTION

Hi @Yamja.,

Open planned_task table in list view, and add the filter "top_task IS PRJ0010113" and get all the tasks related to this particular top task and see if any task is having the Short description as empty.
Since Short description is mandatory Its very confusing that how can any task will not be having a name.
Also there can also be a deleted task which may not be deleted properly and some relationship might have got messed up.
So in planned task table, if you are able to see any task without short description, that need to be updated.

2nd thing to do is, on the master project, open the Project Diagnostics from related links. Use this feature to check  if any task present with "Invalid top task, parent or relation". This can help you to address the issue.

 

let me know if it was helpful.

 

Thanks. 

View solution in original post

5 REPLIES 5

I looked at project short description, It is not empty.

 

For now we are deactivating that business rule. Thanks for your help.