Hi Team,

 

We have a requirement to change the current state to previous state (On Hold to Review State) when the 'Expected in production date' is crossed.

JayN_0-1738594558228.png

 

Thanks, Jay

3 REPLIES 3

Dr Atul - LNG
Tera Patron

Hi @Jay N 

 

There can be 2 ways

 - Schedule job, which can run at mid night and can update the state or

- use Flow designer, which is low code and you can do triggers, and actions - Look up records and then update records. The flow designer is much recommended.

Ankur Bawiskar
Tera Patron

@Jay N 

you can have a flow which runs daily at end of day

Check if the date has crossed if yes then update the state

follow this link where I shared solution and enhance it to update

I cannot seem to get an Email Notification when a record's due date is reached 

If my response helped please mark it correct and close the thread so that it benefits future readers.

@Jay N 

Hope you are doing good.

Did my reply answer your question?

If my response helped please mark it correct and close the thread so that it benefits future readers.