On Project task , change in actual start date calculates and changes planned end date on submission

Aishwarya Pulas
Tera Contributor

On Project task , change in actual start date calculates and changes planned end date after form is submitted. 

I am trying to calculate field poc using dates , so when i try getting the current value of planned end date I get the previous value instead of the value it got changed after submitting.

 

planned end date before hitting the submit button 9/10/2023

post submit the Business rule "Recalculate" does the calculation and changes the date to 10/10/2023

But when I do current . end_date; I get 9/10/2023 instead of 10/10/23.

 

tried shifting logic to client side but the setting is not dynamic but after submission so no use.

 

Since the setting is after submission , my BR is unable to get the latest value.

Any suggestion would be helpful. 

0 REPLIES 0