Hi Team ,
Can anyone please help me with my requirements?
I have created a few custom fields in the 'Analysis Information' section.
when problem tasks is going to close , Those fields should be mandatory , which is not happening
Please see this below screen shot , this Ptask is closed , but fields didn't mandatory .
If i have created UI Policy which is not working .
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-22-2024 02:48 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-22-2024 03:12 AM
Hello,
Currently If a tab has a mandatory field that is empty it will automatically add an asterisk.
That's the expected behaviour.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-22-2024 03:19 AM
Hi @Ravi Gaurav ,
my requirement is to make those custom fields mandatory . when ever state is closed .
@Ravi Gaurav please provide configuration steps
@Ravi Gaurav could you please help me here
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-22-2024 03:22 AM
Please share the UI policy screenshot.