Schedule Span start date and end date

G Balaji
Kilo Guru

Hi,

We're using schedule span to define start and end time. We've defined start and end time with a date as it is expected and set the "Repeats" to daily. Challenge we've now is, start date and end date are not updated everyday though we've set repeats as daily. Because of this, we couldn't process to check if current time falls within schedule or out of schedule.

find_real_file.png

As one could see in the above screenshot, "when" field has date values as 25th July whereas actual date is 13th August. So, when my business rules checks "when" field value it always returns agent is not part of schedule.

Are we missing anything here?

Thanks.

1 REPLY 1

Jyoti8
Kilo Guru

Hi G Balaji,

 

These links might help you.

https://community.servicenow.com/community?id=community_question&sys_id=60bf726ddb58dbc01dcaf3231f96...

 

https://community.servicenow.com/community?id=community_question&sys_id=125b8721db9cdbc01dcaf3231f96...

 

If I have answered your question, please mark my response as correct and/or helpful so that others with the same question in the future can find it quickly and that it gets removed from the Unanswered list.

Thank you