03-16-2023 08:07 AM
I have a question regarding the Change Approval process.
One of the changes that I submitted for approval was approved by my manager and the state went from 'Awaiting Approval' to 'Implementation'. The states are Read Only. Something that I did on the ticket set the Change ticket back to 'Draft' state. I cannot figure out what caused this. I have tried replicating the issue in our dev instance, but has been unable to do so. One thing that I did was to make a change on the 'Communication plan' for the change.
Any idea what might have caused it or how I can better check the Change logs? I have checked the 'History' of the ticket but didnt find anything useful.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-16-2023 08:31 AM
Because the change was first created and approved by everyone (it moves to the implementation state), and then you made some changes to it, I believe it needs to go through all the approvals again!
Please check the workflow of the change to get the more details, here are the steps:
Filter Navigator - > Workflow all contexts -> copy the sys_id of that change and paste it in the ID column, you will get the workflow attached -> click on show workflow
If my answer solved your issue, please mark my answer as ✅Correct & 👍Helpful based on the Impact.