What creates calendar entries on a user’s individual calendar? (Choose two.)
A. Approved resource plan.
B. Allocated resource plan.
C. Confirmed resource plan.
D. Planned resource plan.
Solved! Go to Solution.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-07-2023 01:58 AM
Hello @Mahesh Baraskar ,
In ServiceNow PPM (Project Portfolio Management) application, the following options can create calendar entries on a user's individual calendar:
A. Approved resource plan: When a resource plan is approved, it can generate calendar entries for the allocated resources on the individual calendars of the assigned users. This helps users track their allocated time for specific projects or tasks.
C. Confirmed resource plan: Similar to the approved resource plan, when a resource plan is confirmed, it can create calendar entries on the individual calendars of the assigned users. The confirmed status indicates that the resource plan has been finalized and can be relied upon for scheduling and resource allocation purposes.
If this helped you in any way, please hit the like button/mark it helpful. So it will help others to get the correct solution.
regards,
Prasad
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-07-2023 02:14 AM
@Community Alums I checked on my PDI and the states of resource plan A. Approved and B. Allocated create entry on the user's calendar.
All community users, please check on your PDI and confirm. Thank you.
From my end, correct answer is: A. and B.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-07-2023 01:58 AM
Hello @Mahesh Baraskar ,
In ServiceNow PPM (Project Portfolio Management) application, the following options can create calendar entries on a user's individual calendar:
A. Approved resource plan: When a resource plan is approved, it can generate calendar entries for the allocated resources on the individual calendars of the assigned users. This helps users track their allocated time for specific projects or tasks.
C. Confirmed resource plan: Similar to the approved resource plan, when a resource plan is confirmed, it can create calendar entries on the individual calendars of the assigned users. The confirmed status indicates that the resource plan has been finalized and can be relied upon for scheduling and resource allocation purposes.
If this helped you in any way, please hit the like button/mark it helpful. So it will help others to get the correct solution.
regards,
Prasad
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-08-2024 11:51 PM
Can you give a reference to verify this info?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-07-2023 02:14 AM
@Community Alums I checked on my PDI and the states of resource plan A. Approved and B. Allocated create entry on the user's calendar.
All community users, please check on your PDI and confirm. Thank you.
From my end, correct answer is: A. and B.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-17-2024 11:30 PM
What do you mean by approved Resource Plan? After requested, the only actions possible are "Cancel", "Confirm", "Confirm and Allocate", and "Reject":