ADO integration of Epics into DPR

Yuggi2
Tera Contributor

Hi guys, have integrated ADO and assigned a plan to the application. 
Recently found out that EPICS when created in ADO are the only record type which appear in the Release Planner, which i find strange as generally would be at the story level. 
Also note that I had ADO features which did sync, but when you are in the EPIC record and select Product feature field, those ADO features do not display, assuming that is due to the records in Servicenow class them as work items
So my question is how can DPR work with ADO if EPICs in ServiceNow are classed as platform enhancement records, and stories, features are just work items. 

1 ACCEPTED SOLUTION

Tanushree Maiti
Tera Patron

Hi @Yuggi2 

 

refer:

https://www.servicenow.com/community/digital-product-release-forum/after-integrating-dpr-with-ado-on...

 

https://www.servicenow.com/community/itsm-forum/after-integrating-dpr-with-ado-workitems-are-getting...

 

 

Please Accept the solution if it assisted you with your question & Mark this response as Helpful.
Regards
Tanushree Maiti
ServiceNow Technical Architect
LinkedIn: https://www.linkedin.com/in/tanushreemaiti

View solution in original post

2 REPLIES 2

Tanushree Maiti
Tera Patron

Hi @Yuggi2 

 

refer:

https://www.servicenow.com/community/digital-product-release-forum/after-integrating-dpr-with-ado-on...

 

https://www.servicenow.com/community/itsm-forum/after-integrating-dpr-with-ado-workitems-are-getting...

 

 

Please Accept the solution if it assisted you with your question & Mark this response as Helpful.
Regards
Tanushree Maiti
ServiceNow Technical Architect
LinkedIn: https://www.linkedin.com/in/tanushreemaiti

Yuggi2
Tera Contributor

Thank you, I found this, i struggle with the logic behind this restriction