GRC: Advanced Risk , what is the possiblility of caluclating the score based on questionarrie

Nagasai Ram San
Tera Contributor

what is the possiblility of caluclating the score based on questionarrie responses instead of out-of-the box manual factors and group factors. Is there a way to include scoring part in questionarrie assessment ?

 

NagasaiRamSan_0-1678301342938.png

 

@Gunjan Kiratkar @Community Alums

 

5 REPLIES 5

Connor Levien
ServiceNow Employee
ServiceNow Employee

Hey @Nagasai Ram San ,

 

You can configure automated factors to look at a questionnaire instance and to calculate the risk based on the questionnaire assessment. As part of the questionnaire design using survey designer or if the template is manually built you can give each choice in the questionnaire a score and then in the automated factory you can aggregate these scores in a way you see fit to assess the risk.

Automated factors does however require the enterprise license.

Community Alums
Not applicable

Hi @Nagasai Ram San ,

You are using Advanced Risk Management already as i can see from your screenshot.

So, to achieve the possiblility of caluclating the score based on questionarrie responses , you will need to create a RAM (Risk Assessment Methodology) "//make sure it's in the published state// and under RAM can have different assessment types, where you can create factors which is nothing but the questionarries and you can define the calulations based on these factors.

 

 

To Create a RAM, follow these steps properly :

  1. Navigate to All > Advanced Risk Assessment > Administration > Risk Assessment Methodologies .
  2. Select New .
  3. On the form, fill in the fields.

    For a description of the field values ​​on the risk assessment methodology form, see Risk Assessment Methodology form .

  4. Right-click and save the form.
  5. To configure the various assessments, select one of the following options.
    Choice Related links
    Configure inherent assessment See Configure an inherent assessment .
    Configure control effectiveness See Configure a control effectiveness assessment
    Configure residual assessment See Configure a residual assessment
  6. Select Publish .
    Note: After a new assessment is created on the same risk and the assessment is in the Monitor state, the other assessments automatically move to the Completed state. When an assessment instance is in the Monitor state, you can't move the RAM back to the Draft state. A RAM can only be moved back to the Draft state if there are no assessment instances.