In sla report Business elapsed time and percentage showing 0, kindly help

 

@Ankur Bawiskar

1 ACCEPTED SOLUTION

prudhviraj1
Tera Guru

Hi

Check the schedules, missing on schedule entries and child schedules

 

 

View solution in original post

3 REPLIES 3

Vasantharajan N
Giga Sage
Giga Sage

@Kusuma Sai - there is a kb article related to this issue. Please refer the link below and check.

https://support.servicenow.com/kb?id=kb_article_view&sysparm_article=KB0996566 


Thanks & Regards,
Vasanth

AndersBGS
Tera Patron
Tera Patron

Hi @Kusuma Sai ,

 

Is the Stop time being set to a time before the Start time on the task SLA? If yes, The difference between Start and Stop time will give a negative value, hence you will see 0. 

 

If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

Best regards

Anders

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders

Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/

prudhviraj1
Tera Guru

Hi

Check the schedules, missing on schedule entries and child schedules