Hi Team,

 

I want to create schedule "cmn_schedule_span" 

 

Requirment is 

July-Sep WHs:
9:00 - 15:00 The whole week (Monday to Friday) repeats every year from July 16th to September 15th. Attached a screenshot.

 

AkshataP30_0-1727077713256.png

Repeat until - 2024/09/15

If I add Repeat until then will it run next year from july to september?

 

I want the schedule to run from july 16th to september 15th every year from mon-friday.

 

1 REPLY 1

Dr Atul G- LNG
Tera Patron

Hi @AkshataP30 

 

1st , it is not SNOW, it is SN or ServiceNow.

 

2nd, Repeat until., you need to mention dates till 2025 , 15th Sep not 24. It is same as we have in our outlook. 

*************************************************************************************************************
Regards
Dr. Atul G. - Learn N Grow Together