Hello All,
We have a requirement to add a new holiday schedule. The expectation is to stop the SLA's from running on the holiday on all existing tickets. If we add a child holiday calendar schedule to the main SLA schedule today, will it stop the SLA on all the running tickets which are in already in open state on the Holiday(3 days after)? or it will take only effect on incidents created after the holiday schedule is added? please suggest.
Thanks,
Nagender
Solved! Go to Solution.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-06-2022 02:08 AM
That is correct but it will not update the Breach Time & thus Repar is needed. While other things will be taken care.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-06-2022 02:59 AM
You are absolutely right. Thank you very much. I kind of overlooked breach time.