I'm getting started setting up Change Management and have a couple of questions (assuming a normal type change).
Am I correct that the assess stage is where the business and technical sides complete their work and documentation and that the approval in that stage comes from that part of the organization?
If I am correct, how do I set up so that the correct set of approvers get notified for a given change?
Thanks for any information you can provide.
John
:{)
Helpful and Correct tags are appreciated and help others to find information faster
Solved! Go to Solution.
- Labels:
-
Change Management
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-18-2018 11:04 AM
I've done further research and find that the approvers for assess come from the Assignment Group.
:{)
Helpful and Correct tags are appreciated and help others to find information faster
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-17-2018 12:40 PM
John,
In our organization, while in the Assess stage, the identified Change Manager is the one who receives the notification and must approve the change. Change Manager is a required field at submission of a new Change Request. If the Change Manager on the record is also the person who entered the Change Request our workflow automatically approves the request and moves the record to the Authorize state for the associated CAB member to complete the approval. All of this is done via the workflow.
Hope this helps.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-17-2018 01:22 PM
Thank you Stephen.
That does help. I assume that the change manager is the Assigned To on the change form.
:{)
Helpful and Correct tags are appreciated and help others to find information faster
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-17-2018 01:31 PM
Actually, the Change Manager is a custom field that we set up. But, calling the custom field in the workflow or in the notifications is no different than calling an OOTB field.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-18-2018 11:04 AM
I've done further research and find that the approvers for assess come from the Assignment Group.
:{)
Helpful and Correct tags are appreciated and help others to find information faster