Set Due Date to be 14 days prior to Go-Live Date

jherrell
Giga Contributor

I have a custom form that I have setup.  I have a custom field on my task that is labeled as "Go-Live Date".

On my subtask, I have a field labeled as "Due Date".

My subtasks are set to auto-generate upon submitting the initial task. 

I need the "Due Date" field to auto-set for 14 days prior to the "Go-Live Date" on the parent task.

 

What is the best way to accomplish this?

5 REPLIES 5

Hi,

Glad you got it all resolved. If any particular post contain code that you used or guidance that you used, please mark that as Correct? I know for my post I covered both Date and Date/Time to assist either way. It seems you ended up using Date method?

Anyways, the core question I think was still answered as far as the calculation and correct way to go about it within SN.

Thanks and take care!