Set Due Date to be 14 days prior to Go-Live Date
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-19-2019 08:11 AM
I have a custom form that I have setup. I have a custom field on my task that is labeled as "Go-Live Date".
On my subtask, I have a field labeled as "Due Date".
My subtasks are set to auto-generate upon submitting the initial task.
I need the "Due Date" field to auto-set for 14 days prior to the "Go-Live Date" on the parent task.
What is the best way to accomplish this?
- Labels:
-
Request Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-13-2019 01:08 PM
Hi,
Glad you got it all resolved. If any particular post contain code that you used or guidance that you used, please mark that as Correct? I know for my post I covered both Date and Date/Time to assist either way. It seems you ended up using Date method?
Anyways, the core question I think was still answered as far as the calculation and correct way to go about it within SN.
Thanks and take care!
Please consider marking my reply as Helpful and/or Accept Solution, if applicable. Thanks!