Unable to set Milestone and Key Milestone on the Project task form

kjay
Giga Contributor

Our customer instance is in London. When we try to select the checkbox milestone or key milestone, then save the changes, the checkbox got unchecked. Any idea if this is the OOB behavior for the project task? find_real_file.png

1 ACCEPTED SOLUTION

sachin_namjoshi
Kilo Patron
Kilo Patron

Milestones are project task with duration of 0.

Please follow below to create miltstone for your project.

 

https://docs.servicenow.com/bundle/london-it-business-management/page/product/project-management/task/t_CreateMilestones.html

 

Regards,

Sachin

View solution in original post

3 REPLIES 3

sachin_namjoshi
Kilo Patron
Kilo Patron

Milestones are project task with duration of 0.

Please follow below to create miltstone for your project.

 

https://docs.servicenow.com/bundle/london-it-business-management/page/product/project-management/task/t_CreateMilestones.html

 

Regards,

Sachin

Yup! I saw that as well. Do you have an idea about the key milestone? I can't set a Project task as key milestone.

nicolesantikko
Tera Contributor

Hi there - did you ever receive any more information on this?  I am having the same question come up where our team is trying to flag milestones and key milestones on existing tasks and its wiping out the dates and unchecking the boxes when saving. I don't understand how a milestone is supposed to be used if the duration has to be 0?