Breakdown on Risk table - PPM - Project Manager - How?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
23m ago
I need to create a breakdown mapping on the risk table by project manager so that I can provide KPI breakdown by PM responsible for the project to which a given risk relates. The table definition for the risk table provides "Top Task" as a reference to Task, and when viewed the risk table displays "PRJXXXXX" in this column. In the breakdown mapping form ("New Record") when attempting to create this relationship however the project manager field is not available under the "Top Task" choice. There are lots of other fields available, but Project Manager is not present. Why is this and how can I create this mapping? It's possible to create this mapping for a visualization (list view), expect same behavior here. Thank you for any advice provided.