I'm trying to create a PA Dashboard for our CIO. He has very specific requirements. I'm trying to mock this up using incident to show New, In Progress, Closed with a trend line of backlog (anything still in progress). I'm able to do this but because of the way the out of the box indicators are counting I'm not getting distinct occurrences of each incident so they may be counted multiple time in one month. Example screenshot below showing that open incidents are in the 20 thousand which is incorrect. Is there a way to get the correct number without changing any of the out of the box indicators or sources? 

BrianLancaster_0-1678830653217.png

 

1 ACCEPTED SOLUTION

AndersBGS
Tera Patron
Tera Patron

Hi @Brian Lancaster ,

 

i would always recommend to create your own indicator source, automated indicator and formula indicators, to ensure it’s configured according to your requirement and that you retrieve the expected data.

 

so from my perspective, start configuration from scratch and build the PA reports according to the CIO requirement.

 

if my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

Best regards

Anders

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders

Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/

View solution in original post

4 REPLIES 4

AndersBGS
Tera Patron
Tera Patron

Hi @Brian Lancaster ,

 

i would always recommend to create your own indicator source, automated indicator and formula indicators, to ensure it’s configured according to your requirement and that you retrieve the expected data.

 

so from my perspective, start configuration from scratch and build the PA reports according to the CIO requirement.

 

if my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

Best regards

Anders

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders

Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/

I was thinking that might be the answer. So question, they want this by month so I'm guessing it would be best to set the indicator source to month. However I'm not sure how to do the scheduled jobs since each month is not the same.

Hi @Brian Lancaster .

 

This is an example of a job that I have in my PDI that runs on monthly basis:

AndersSkovbjer_0-1678862735913.png

if my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

Best regards

Anders

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders