I need to create a report in ServiceNow that dynamically displays all changes scheduled between this week's Tuesday and next week's Monday. I tried to play around with the "trend" and "relative" operators, but could not come up with something that displays only this range. After all, it's not "this week". Any ideas? 

1 ACCEPTED SOLUTION

AndersBGS
Tera Patron
Tera Patron

Hi @Brasa ,

 

you should be able to create a report with the conditions:

 

schedule on this week and

S schedule  relative after Tuesday 

OR

schedule on next week and

schedule relative before Monday 

 

its important to have the big OR i between the two conditions, otherwise it will not work .

 

If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

Best regards

Anders

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders

Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/

View solution in original post

5 REPLIES 5

Brasa
Tera Contributor

Thank you very much! It works like a charm!