RITMS getting closed incomplete, apprpoval of RITms getting rejected when Request Approval is reject

Annirnita Dash1
Tera Contributor

Hello Folks,

Please help me to know why the related RITMs of a single request gets "closed incomplete" and its approval field  gets rejected (even when they are in OPEN) when the REQ's state is Closed incomplete and approval is rejected. 

It OOB configured somewhere.

 

I have a requirement where I need to set the REQ "approval" as rejected, stage as "closed cancelled", state as " "closed incomplete" even  when 

Request is having multiple RITMs and Any one RITM 1 is Closed Incomplete and RITM 2 is Open.

Upon trying to achieve this, I was setting "REQ" approval as rejected when any RITM's approval is rejected and got all related RITM as closed incomplete.

Please help if anyone can understand this use case.

 

1 ACCEPTED SOLUTION

@Annirnita Dash1 

there is some custom flow or business rule which is doing this.

Ideally if it's OOB then it should only impact the RITM for which the approval was rejected under that REQ and not the other RITM under the same REQ

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
Certified Technical Architect  ||  9x ServiceNow MVP  ||  ServiceNow Community Leader

View solution in original post

10 REPLIES 10

Reus
Tera Expert

There might be some BR which will be working in it.

is there any OOB?

Ankur Bawiskar
Tera Patron
Tera Patron

@Annirnita Dash1 

did you use script tracer to debug?

Script Tracer and debugging scripts 

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
Certified Technical Architect  ||  9x ServiceNow MVP  ||  ServiceNow Community Leader

Hi Ankur, yes I have used it, but could not find anything where values of REQ's fields are changing RITMs.