Assigned To field will not populate based on Assignment Group for Project Task

etobia
Kilo Expert

This works flawlessly in Incident, Request, and Change. However, when i create Project Task for Project, look up for Assigned To field is empty when a Assignment Group is selected. Any thoughts???

1 ACCEPTED SOLUTION

Michael Fry1
Kilo Patron

There is an out of the box Dictionary Override on Project Task table. If you want to be dependent upon Assignment Group, you need to remove the override:



Screen Shot 2016-08-26 at 5.35.20 PM.png


View solution in original post

9 REPLIES 9

Abhinay Erra
Giga Sage

Do you have any script for this? If yes post the script


Michael Fry1
Kilo Patron

There is an out of the box Dictionary Override on Project Task table. If you want to be dependent upon Assignment Group, you need to remove the override:



Screen Shot 2016-08-26 at 5.35.20 PM.png


Thanks Michael. That worked. I set the values to false for the pm_project_task table.


What is the expected out of box behavior for this reference qualifier? We're having the same issue, and would like to understand this before disabling it.