How Cost plan related Cost break downs are calculated ?

One user reported that , Cost plan of FY22 all months break down "Entered cost and functional cost" updated automatically

Where its get updated ? where calculates the value ?

find_real_file.png

1 ACCEPTED SOLUTION

@Sukran  - You fiscal period for above screenshot seems to be 20 months

 

Calculation logic of Total planned cost

Now you manually enter Unit cost and quanitty
Servicenow will automatically calculate Total planned cost as Unit cost*quanitity = 25000*1 = 25000

 

Calculation logic of Entered cost

Now the on cost plan breakdown's entered cost is calculated as Total Planned cost/Fiscal period (in months)

= 25000/20 = 1250

ts gets updated at at : cost_plan_breakdown table.

Functional cost uses Exchange rate is used to convert entered cost into functional cost. It is obtained from the itfm_fx_rate [budget_reference_rates] table.

Please let me know if this clarifies.

Thank you!
Rajesh

 

If you found my response helpful or applicable, please consider marking it as correct or helpful to assist others who may be seeking the same information.

---------------
Regards,
Rajesh Singh

View solution in original post

8 REPLIES 8

Rajesh_Singh
Kilo Sage
Kilo Sage

Hi Sukran,

Entered cost is breakdown of total cost/fiscal period.

For example

On Cost plan form : you entered Unit cost as 500 and quantity as 5 then Total planned will be 2500 USD for fiscal period of 10 months

On Cost plan breakdown :

Entered cost will be = total cost/Total fiscal period in Months = 2500/10 = 250 USD
Functional cost will be calculated based on Functional currency selected = Say functional currency selected as EUR then Functional cost will be 245 (since 250 USD = 245 EUR)

Its gets updated at at : cost_plan_breakdown table.

Functional cost uses Exchange rate is used to convert entered cost into functional cost. It is obtained from the itfm_fx_rate [budget_reference_rates] table.

Please do mark this as helpful and correct. if this able to help you.

Thank you!
Rajesh Singh

If you found my response helpful or applicable, please consider marking it as correct or helpful to assist others who may be seeking the same information.

---------------
Regards,
Rajesh Singh

@Rajesh Singh  Thanks , But our quantity as 1 , but when total planned cost is changed 

its applied automatically entire months FY21 Start and FY22 DEC with calculates

Can you pls send me screenshot of cost plan? also please do let us know is cost plan auto created through resource plan or it was created manually

If you found my response helpful or applicable, please consider marking it as correct or helpful to assist others who may be seeking the same information.

---------------
Regards,
Rajesh Singh

@Rajesh Singh Checked its manual creation 

Its due to manual creation ?

 

Cost Plan Screenshot:

find_real_file.png

 

Cost break down

find_real_file.png