Different Sprint schedules per ART

art_jones
Kilo Sage

Is it possible for different ARTs to use different sprint schedules when using the same PI? We are running Enterprise Agile in SPM on Xanadu.

If I have a sprint setup for Team 1 (Apr1-Apr14), and then I attempt to setup another for Team 2 who follow a different schedule (Apr2-Apr16) then I get an error "Calendar entries should not overlap within a calendar".  Is there a way to do this?  Thanks!

1 ACCEPTED SOLUTION

art_jones
Kilo Sage

My issue was that my Agile config was setup to synch with Agile 2.0 and this prevents overlapping sprints (by design).

 

View solution in original post

6 REPLIES 6

Brian Lancaster
Tera Sage

Unless something has changed in Xanadu. There should be a group dropdown on the planning board. If you change the group to Team 2 you should be able to create a separate sprint with different time lines.

BrianLancaster_0-1738167128526.png

 

Hi Brian;

Thanks for responding!  Yes, the UI for all of this changed significantly in Xanadu.  Unfortunately as far as I can tell, that dropdown doesn't exist in the workspace.

Regards, Art

Natalie Hunter
Tera Contributor

Hi Art

In SAFe it is typical that teams within the SAME ART sprint on the same cadence.  There is some automation in SAFe that automatically generates a sprint for each of the teams in the ART when the PI is created.  It might be worthwhile checking if a sprint has already been created for that Team in that specific PI, as there are checks in place to ensure that sprints do not overlap, even by one day.

So the conclusion is that sprints cannot overlap within the same ART? I am facing the same issue