Is it possible for different ARTs to use different sprint schedules when using the same PI? We are running Enterprise Agile in SPM on Xanadu.
If I have a sprint setup for Team 1 (Apr1-Apr14), and then I attempt to setup another for Team 2 who follow a different schedule (Apr2-Apr16) then I get an error "Calendar entries should not overlap within a calendar". Is there a way to do this? Thanks!
Solved! Go to Solution.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 12:47 PM
My issue was that my Agile config was setup to synch with Agile 2.0 and this prevents overlapping sprints (by design).

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 12:46 PM
If "Synch sprint with Agile Development 2.0" is checked in your Agile config, you cannot overlap sprints.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 12:47 PM
My issue was that my Agile config was setup to synch with Agile 2.0 and this prevents overlapping sprints (by design).