Is it possible for different ARTs to use different sprint schedules when using the same PI? We are running Enterprise Agile in SPM on Xanadu.

If I have a sprint setup for Team 1 (Apr1-Apr14), and then I attempt to setup another for Team 2 who follow a different schedule (Apr2-Apr16) then I get an error "Calendar entries should not overlap within a calendar".  Is there a way to do this?  Thanks!

1 ACCEPTED SOLUTION

art_jones
Kilo Sage

My issue was that my Agile config was setup to synch with Agile 2.0 and this prevents overlapping sprints (by design).

 

View solution in original post

6 REPLIES 6

If "Synch sprint with Agile Development 2.0" is checked in your Agile config, you cannot overlap sprints.