Hybrid Projects and Agile Application

davidsmith
Tera Expert

Hello,

I am looking into using Hybrid projects in ServiceNow. In my scenario I have an Agile Product called Change Agent Work. We have started to populate the product with stories, assigned to a group, setup a backlog etc. We also have a project called Change Agent Work where I have setup the execution type to be Hybrid and I have set-up an Agile Phase.

My question is can I link up the Agile Phase to my existing Agile Product? I am expecting to be able to be able to use the Project Workbench manage existing stories, boards etc, Or is the assumption that if you are using the Agile Phase in project you are essentially craeting stories from scratch and NOT wanting to link up to an existing product.

Thanks in advance

David

PS I am familiar with the documentation

https://docs.servicenow.com/bundle/quebec-it-business-management/page/product/project-portfolio-suite/concept/c_CreateAndManageAgileProjects.html?cshalt=yes

1 ACCEPTED SOLUTION

Sulabh Garg
Mega Sage
Mega Sage

Hello Davidsmith,

In Project Agile phase, I do not see option to link the Agile product, However you can link the stories, Epics present in agile product to agile phase using related list on Agile phase. Technically, I don't think there is any assumption/issue where you can't link the existing stories/Epics of your Agile product with Agile phase on projects.

Epics related list is not present on Agile phase, you may need to bring under related list.

Hope it helps.

find_real_file.png

 

Please Mark ✅ Correct/helpful, if applicable, Thanks!! 

Regards

Sulabh Garg

Please Mark ✅ Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg

View solution in original post

3 REPLIES 3

Sulabh Garg
Mega Sage
Mega Sage

Hello Davidsmith,

In Project Agile phase, I do not see option to link the Agile product, However you can link the stories, Epics present in agile product to agile phase using related list on Agile phase. Technically, I don't think there is any assumption/issue where you can't link the existing stories/Epics of your Agile product with Agile phase on projects.

Epics related list is not present on Agile phase, you may need to bring under related list.

Hope it helps.

find_real_file.png

 

Please Mark ✅ Correct/helpful, if applicable, Thanks!! 

Regards

Sulabh Garg

Please Mark ✅ Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg

Hi Sulabh,

Thanks for your reply. I will keep on investiagating to if I can incorporate existing products into the Agile phase.

Many thanks

David 

Chris Ashe
Tera Contributor

Hi - Did you mmake any traction on this?