Link between State and Percent Complete in Project

Farfara
Tera Contributor

Hello,

How can I modify the link between the state and the percent complete fields.

When I change the state to "Work In Progress", the percent compte will be 0% when I want it to keep the same value.

 

Farfara_0-1711713386372.png

 

I would like :

State "Closed skipped" or State "Closed incomplete" -> we let the 'Percent complete' as it is mentionned by Project Manager (= we do not modify it for 100%)

State Closed complete -> the percent complete must be 100% (as today)

State Open -> we let the 'Percent complete' as it is mentionned by Project Manager (= we do not modify it for 0%).

 

Regards,

 

FF

6 REPLIES 6

Sohail Khilji
Kilo Patron
Kilo Patron

HI @Farfara ,

 

Navigate to busienss rules.

Search for > Set State On Percentage Change. This is responsible for percentage change. Adend this business rule and that must help you..

 

based on you project requirement  you can make change and try... i hope this helps...


☑️ Please mark responses as HELPFUL or ACCEPT SOLUTION to assist future users in finding the right solution....

LinkedIn - Lets Connect

Farfara
Tera Contributor

Thanks @Sohail Khilji but this business rules is for project task, I'm in the project form. 

 

Regards,

 

FF

Hi @Farfara ,

Hope you are doing well.

Similar question was asked few weeks back for which I created a recording.

Please refer this link.

 

Hopefully you would find it useful. In case, you still have question, please post and will look into it.

 

Thank You!

Namita Mishra

 

Farfara
Tera Contributor

@Namita Mishra Thank you, explainations  in the videos are clear but what about the "Open" State, in my case, It would not be 0%. I would remain the value putting by the PM. 

 

Regards,

 

FF