New item is created successfully but is not on the planning board, as it does not meet the portfolio

Kelsey Douglas
Tera Guru

Can anyone explain to me in detail why this message displays:

 

"New item is created successfully but is not on the planning board, as it does not meet the portfolio plan criteria."
 
Someone asked this question in a previous post, but the response did not answer the question. I have tested a lot of different scenarios to try and figure out what the "portfolio plan criteria" is that my planning items are not meeting, but I am at a loss. I usually get this error when I use a lens, and when defining the lens for my portfolio plan I choose an entity type that is NOT the bottom entity. Even if I reference selected entities when creating a new planning item, I will still sometimes get this error. 
1 ACCEPTED SOLUTION

I figured out that unless the bottom entity of the lens hierarchy has a value, it will not be visible in the portfolio plan in SPW. So for example with the Organization Lens, it has three levels, Company>Business Unit>Department, each planning item has to have a Department assigned to it, otherwise it will not be available. Even if the other levels of the hierarchy (Company and Business Unit) have values. 

View solution in original post

19 REPLIES 19

Shantharao
Kilo Sage

Hi,
Did you get the answer to your question, I am also facing the same issue
few of the newly created and old demands were not visible on the Strategic planning workspace.
Do you know the criteria?
Thanks

 
 
 

I figured out that unless the bottom entity of the lens hierarchy has a value, it will not be visible in the portfolio plan in SPW. So for example with the Organization Lens, it has three levels, Company>Business Unit>Department, each planning item has to have a Department assigned to it, otherwise it will not be available. Even if the other levels of the hierarchy (Company and Business Unit) have values. 

Could you please tell me how the planning item("sn_align_core_demand") gets approved and generate actual demand ("dmn_deman")?
When the execution URL field will be mapped into the planning item table?

In order for a new demand on the "sn_align_core_demand" table to be mapped to the "dmn_demand" and "sn_align_core_planning_item" table, you have to go to All>Strategic Planning>Integrations, open ServiceNow Internal, and click "Generate Default Mappings Configurations". This should create an integration between the two demand tables, and it will also add the demand to the planning item table.